Clandestine Laboratory, Training and Research Center, Department of Justice DEA, in Quantico, Virginia
A General Contractor Serving Washington, DC Metropolitan Area Since 1951

BID SCHEDULE AS OF THURSDAY 8/22/2019

Bid Date Project Location Estimate
8/26/2019 GSA 11 D/B Steam Station Replacement Project, Howard T. Markey National Courts 717 Madison Place, NW, Washington, DC 20439 $500,000-$1 Million
5:00P GSA (47PM0419Q0042 Amnd. 6) CMD: Ddg:
The existing steam stations are a single stage type system, fed by a 250 psi line from HOTD. The building houses two current steam stations, both in a 250 PSI x 15 PSI single-drop configuration. One steam station serves the three houses, the other serves the Markey core building. This configuration is causing failure of pressure regulators at unexpected times, including shattered valves due to drastic drops. Additionally, piping in not correctly sized. This project shall replace both existing single-drop steam station with a 250 PSI x 100/60 x 15 drop system, including new valves, gauges, piping, and insulation. The building has a third steam station for HVAC that is abandoned. This station needs to be removed and finishes repaired. The main hot water circulating pumps are located immediately adjacent to the steam station. Each of the five pumps is improperly attached directly to concrete pad. Each of the five circulating pumps needs to be modified with a proper inertia base installed. At the horizontal entry of the high-pressure steam into the building, there is no dirt-trap clean out at the bottom of the riser. The piping shall be modified to include proper clean out trap.
8/27/2019 GSA 11 D/B DOE Restroom Renovation, Germantown Campus 19901 Germantown Rd., Germantown, MD 20874 $5-10 Million
4:00P GSA (47PM0519R0016 Amnd. 2) CMD: Ddg:
The building was designed and constructed using imperial units. All dimensions shall be in imperial units with no metric equivalent. The Department of Energy Germantown Complex is comprised of a main building and six satellite buildings and was constructed in 1957-1958 by the old Atomic Energy Commission. The facility is located at 1990 l Germantown Road in Germantown Maryland. The main building is approximately 567,000 sq ft and houses approximately 1,600 workers. DOE's Germantown Main Building restrooms are original and have not been modernized or renovated since the building was constructed. The fixtures, functionality and layout need to be brought up to date and brought into compliance with the Americans with Disabilities Act. The main building consists of approximately 30 multi fixture restrooms, 8 unisex restrooms, 8 mixed shower/restrooms and 2 shower rooms. Provide a design-build project that incorporates the recently completed design referenced in Section V by Geier Brown Renfrow Architects, LLC (GBR) and adds design and construction work for the disciplines of fire and life safety, plumbing, electrical and mechanical as indicated in Section IV, Scope of design/Build Services below. The project shall be divided into four phases as laid out in the referenced GBR design. The complete additional design including incorporation into the GBR four phase design drawings shall be included in Phase I of this project (base contract). The Notice To Proceed for the construction shall be issued after approval of the final design submission incorporating the new work into the existing GBR design. The four phases of construction for the project will be performed as a base contract with three options based on the four phases in the GBR design with priorities for the phases being determined based on the needs and requirements of the Department of Energy. The base contract will include the full design as stated in this SOW and phase 4 of the GBR design for E and G Wings and the Warehouse. The three options are the GBR design phases l through 3 and will be awarded as determined by the Department of Energy.Demolition shall include removal of all wall boarding, tile, flooring, fixtures, electrical wiring, lighting, plumbing, and water and waste risers. Design should lay out the optimum placement of the fixtures and achieve the highest level of functionality within the space available as well as complying with the Architectural Barriers Act Accessibility Standard (ABAAS) for the building. The final design package shall also ensure adequate ventilation and air movement in all restrooms. The final design and construction package shall include all drawings, specifications and documentation for demolition and renovation of the restrooms and shower facilities with completion of the project in the four phases.
8/28/2019 Munitions Load Crew Training Facility at Joint Base Andrews, Project No. AJXF039040 113th Wing, 3252 Perimeter Road, Joint Base Andrews AFB, MD $1-5 Million
2:00P Dept of the Army National Guard Bureau (W912R1-19-B-5002 Amnd. 4) CMD: Ddg:
The project will be LEED® Silver Certified. The requirement will consist of the construction of a new Munitions Load Crew Training Hangar, with supporting facilities, for a total of 8,279 gross square feet of new construction. Support facilities include toilets, offices, a classroom, and storage and support spaces. All work shall be accomplished in accordance with applicable drawings, specifications, industry standards, building and environmental codes, regulations, and laws. Moreover, the Contractor shall comply with ALL applicable Unified Facilities Criteria (UFC) and Air National Guard Engineering Technical Letters (ANG ETL); in addition to federal, state, and local regulations. In addition to a base price for the work described above, the solicitation will include Government Options (Additive Bid Items (ABI).
8/30/2019 AFICA EAST D/B Repair Roof for Aircraft Hangar Building 1511, Shaw AFB, SC Shaw AFB, SC $1-5 Million
5:00P Dept of the Air Force (FA4803-19-R-R002 Amnd. 3) CMD: Ddg:
The contractor shall provide all labor, material, equipment and transportation, and perform all operations necessary to accomplish the following items of work in accordance with Shaw Design and Construction Standards dated 21 August, 2018, change 2, International Building Code (IBC), International Energy Code (IEC), National Electrical Code (NEC), National Electrical Safety Code (NESC), Sheet Metal and Air Conditioning Contractor’s National Association, Inc. (SMACNA), Unified Facilities Criteria (UFC) and National Fire Protection Association (NFPA), latest editions. Drawings and/or Specifications as provided shall be updated to meet the latest UFC, IBC and all other codes. Scope of Work 1. Provide an asbestos and lead based paint survey of all area to be disturbed. 2. Provide a complete design. 3. Remove existing metal roof system and any other material as required to accomplish the work. The insulated panels below the metal deck may remain in place unless they interfere with the new roof system. 4. Install new steel deck and hydrokinetic standing seam metal roof system with permanent Horizontal Lifeline (HLLs) anchorage system for use as a personal fall arrest system. 5. Install gutters and downspouts at each end of the building and as needed to remove water. 6. Tie downspouts into the storm drainage system. 7. Remove the tree and bush behind bays 4 and 5 respectively. 8. Provide a more efficient ridge vent at the roof of each building to help remove water and to keep water from infiltrating the interior of the building.
9/5/2019 GSA 11 VA Affairs Headquarters Canteen Renovation, VA Bdg. VA Bldg., 810 Vermont Ave., NW Washington, DC 20571 $2-2.5 Million
12:00P GSA (47PM0219R0026 Amnd. 1) CMD: Ddg:
The building which dates back to the 1940’s is an 11 story historic structure with three levels below grade. It was modernized in 1994. The canteen was included as part of that modernization. No other renovations have occurred to the space since then. No historic fabric is affected by the scope of work area for the project. Renovation of the existing cafeteria, the Patriot Café, located on level C which is one level below grade in the Veterans Administration Building at 810 Vermont Avenue. Work includes the renovation of approximately 9,120 square feet of kitchen, servery and dining space as indicated in the Construction Documents by Cho Benn Holback. Compliance With Regulations: All work, including contact with and handling of hazardous materials, the disturbance or dismantling of structures containing hazardous materials, and/or the transport and disposal of hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926, and 40 CFR 761/260-271. a. All thermal systems insulation (i.e., boiler insulation, duct insulation, pipe insulation), surfacing materials (i.e., plaster and sprayed-on fireproofing) and miscellaneous materials (i.e., asphalt flooring, ceiling tiles, adhesives and mastics, drywall, roofing, gaskets and cement board), installed no later than 1980, must be considered asbestos containing unless proven otherwise in accordance with 29 CFR 1926.1101. Work involving the disturbance, dismantling or demolition of asbestos containing materials or structures containing asbestos; and/or the removal and disposal of asbestos, shall also comply with the requirements of 40 CFR Part 61, Subparts A and M, and 29 CFR 1915.1001 (where applicable), as well as GSA Specification 02085 (Asbestos Abatement Procedures). b. All finished/painted surfaces of buildings constructed prior to 1978 shall be considered finished with lead based paint unless proven otherwise. Work involving the disturbance, dismantling or demolition of lead based paint shall comply with 29 CFR 1926.62, as well as GSA Specification 02090 (Lead Based Paint Abatement Procedures). It shall be the responsibility of the Contractor to adequately test and characterize the waste by the toxicity characteristics leaching procedures (TCLP) – Lead.
9/5/2019 NIH Tier 1 Building 13 Ground Floor Projects NIH Bethesda, MD
2:00P NIH (C102579 Multi Amnd. 0) CMD: Ddg:
The ORF (Office of research facilities, NHLBI (National Heart, lung and blood institute and NINDS (National Institute of Neurological Disease and Stroke) are planning for multiple projects in the building 13 basement to support several programs. The new program space will be provided through renovation in Building 13. The renovation of this project will house staff scientists and support staff. There are several projects in building 13 basement that are currently under design, construction or planning. Currently we have several contractors and designers on board working on these projects. The building 13 basement layout below demonstrates projects within the ground floor that need to be taken in to consideration during construction: recently completed, in close-out, under construction, in planning and then the five projects to be awarded under this RFP. C102574 - NINDS Machine Shop, C104673 - Mechanical Room, C104856 - DFOM Offices & Front Desk, C105008 - NHLBI Arctica TEM, C105081 - NHLBI Catheter Fabrication Lab
9/5/2019 Navy SDVOSB Western: D/B BEQ 53451 Repair and Repair Channel Marine Corps Base Camp Pendleton CA 53 area (Horno), Marine Corps Base Camp Pendleton CA $5,730,858
2:00P NAVFAC Southwest (N62473-14-D-0069X067 Amnd. 0) CMD: Ddg:
Project will repair BEQ 53451 with 64 units at 53 Area, Horno, Marine Corps Base, Camp Pendleton for the continued use of the 1st Marine Regiment billeting. BEQ 53451 is a 29,442 square feet, two story concrete masonry unit (CMU) structure built in 1975. The existing building is in poor condition and requires work to bring it up to current Building Code and life safety standards. The building was last repaired in 2009 with minimal life, health, safety, and quality of life work, and still needs major repair work It needs general repair of accumulated wear and tear along with upgrades to plumbing systems and fixtures, electrical systems, windows and doors, locks, fan coil units and general architectural finishes.
9/9/2019 FRR MATOC D/B Provide Reconfiguration and Interior Renovation for Keystone Lobby and Visitor Center RKB Facility Repairs, NCIS, Quantico, VA $500,000-1 Milliom
9:00A Dept of the Army, Huntsville (FRR-2019-017840 Amnd. 4) CMD: Ddg:
The objective for this Statement of Work (SOW) is to provide all management, labor, equipment and material necessary for: reconfiguration and interior renovation for Keystone Lobby and Visitor Center at Quantico, VA. Interior Renovation and Repairs include as minimum architectural, electrical, and furniture improvements. The Contractor’s efforts shall comply with the specifications and requirements contained herein. The project requirements and technical criteria cited within this SOW establishes minimum standards for construction quality.
9/10/2019 HR SB MACC Fire Alarm Loop 5 Replacement, NNSY Norfolk Naval Shipyard, Scott Center ANnex and New Gosport Annex, Portsmouth, VA $5-10 Million
2:00P NAVFAC Mid-Atlantic (N40085-19-R-7429 Amnd. 0) CMD: Ddg:
The work includes replacing the existing Fire Alarm Loop 5 at Norfolk Naval Shipyard, Portsmouth, Virginia with a wireless system which consists of wireless transmitters, and incidental related work.The work is located at the Norfolk Naval Shipyard, Scott Center Annex and New Gosport Annex.
9/11/2019 Combat Capabilities Development Command (CCDC) Building 3072 Renov. APG Aberdeen Proving Ground, MD 21005 $10-25 Million
11:00A Dept of the Army (W912DR19B0018 Amnd. 0) CMD: Ddg:
The project is to renovate historic building 3072 to support CCDC, APG, Aberdeen, Maryland. The full renovation of 45,630 SF (4,239 SM) historic facility for continued use by a two star HQ command for continued administrative use. Work will consist of Hazardous Material abatement and demolition, demolition of non-load bearing interior walls, the reconfiguration of walls and ceilings, and ABA compliance. Work will include removal and replacement of building HVAC systems, plumbing systems, electrical systems, fire suppression and alarm/mass notification systems, utility management control, telephone, advance communication networks, cable television and infrastructure for and installation of complete electronic security systems (ESS) (i.e. intrusion detection, closed-circuit surveillance and electronic access control). New interior spaces will be created which include offices, open office areas, conference rooms, break rooms, restrooms, secured space requirements per ICD-705, utility support spaces and new interior stair towers. New interior finishes will be provided throughout the building. Replace basement windows, repair all other building windows. Exterior site-work and utilities include repairing drainage problems to eliminate ponding along the foundation of the building, a new underground fire water main and post indicator valve, electrical, water, gas, sanitary sewer and information systems distribution, utility screening. The construction contract will also include separate packages for the procurement and installation of furniture, furnishings and industrial/manufacturing type equipment, IT/communications and for electronic surveillance systems (ESS).
9/12/2019 AFICA EAST Repair HVAC Multi VLSB 14-0031 at Shaw AFB, SC Buildings 160, 417, 825, 1213, and 1900, Shaw AFB, SC $10-25 Million
1:00P USAF (FA4803-19-R-R001 Amnd. 3) CMD: Ddg:
9/13/2019 AOC CPP Cooling Tower Renovation and Electrical Upgrade RPR Phase IV - Step 2 Refrigeration Plant Revitalization, Capitol Power Plant, 25 E Street SE., Wash., DC 20003 >$10 Million
5:00P AOC (RFPPPA190087 Amnd. 2) CMD: Ddg:
The work of Phase 4 is as follows: a) Base Bid – Internal structural repairs to two (2) WRP cooling towers, component upgrades to two (2) WRP cooling towers, and replacement of the WRP’s 480/277V secondary unit substation. b) Option 1 – Provide perimeter basin protection for Cooling Towers Nos. 1 and 2 as identified on Drawing A731. c) Option 2 – Provide full basin protection for Cooling Towers Nos. 1 and 2 as identified on Drawing A731. d) Option 3 – Provide cost to install all new high performance ceramic fill within the two (2) WRP cooling towers. e) Option 4 – Rehabilitate the existing freight elevator in the WRPE.
9/19/2019 FRR MATOC Sanitary Sewer Repairs, Fort Detrick Fort Detrick, MD 21702 $5-10 Million
11:59P Army, Huntsville Engineering and Support Center (FRR 19-020135 Amnd. 0) CMD: Ddg:
The objective for this Statement of Work (SOW) is to provide all management, labor, equipment and material necessary for: repair by replacing sanitary lines at Ft Detrick, MD. Contractor shall provide repairs by replacement of sanitary lines in support of Facility 2036 (linear structure) gravity sanitary sewer system for Fort Detrick Area A. The current storm water system is overcharging the sanitary system causing sanitary sewer overflows (SSO). The storm water is burdening the waste water treatment plant’s current treatment capacity and limiting future installation expansion capacity within the collection system. Major increases in waste water treatment processing and ad-hoc emergency repairs and response costs are caused by this condition. Major sections of the system are severely deteriorated, unreliable, and inefficiently transporting effluent. Sections are obsolete in design and materials and do not comply with code, engineering criteria, current engineering requirements. This effort includes disconnecting and redirecting storm water lines, mechanical trench cut and fill, and potential abatement and disposal of asbestos cement (AC) pipe in some locations as required.
FRR MATOC D/B General Office Renovations at Raven Rock Mountain Complex, PA Raven Rock Mountain Complex, PA
USACE Omaha District (RFP OMH1 Amnd. 0) CMD: Ddg:
The detailed Statement of Work for this task order has been classified secret, and therefore will be provided to the qualifying Contractors following proper security protocol. At the pre-proposal Site walk more details will be discussed involving classification, & escort requirements for the contractor. In general this project will entail the renovation of administrative type areas and asbestos abatement activities of those areas, as well as possibly more industrial type areas. Using Design-Build approach this project will consist of the following elements; 2.1 Base Contract: 2.1.1 Room renovations: Approximately 30 rooms have been identified to be renovated due to their age. Rooms are comprised of berthing rooms, offices, storage rooms and computer labs. The room renovations shall be constructed in two (2) successive phases. Phase 1 work must be totally complete, and operational before Phase 2 work is started. Phase 1 to be completed 365 calendar days from Notice to Proceed (NTP). Phase 2 to be completed 300 calendar days from completion of Phase 1. Rooms assigned to each phase are defined in the aforementioned detailed Statement of Work, provided at the pre-proposal Site walk. 2.1.2 One unisex bathroom renovation: The existing unisex bathroom shall be totally demolished, and renovated without urinals to maximize the number of toilets and showers. Period of Performance to be completed within the timeframes stated in paragraph 2.1.1 above. 2.1.3 Abatement of Hazardous Materials & Affected Materials & Equipment for all work locations within existing defined corridor hallways and associated work areas. Period of Performance to be completed within the Phase 1 and Phase 2 timeframes stated in paragraph 2.1.1 above. 2.1.4 Design and installation of a Supply & Return Duct System located within existing defined corridor hallways and associated work areas. Period of Performance to be completed within the Phase 1 and Phase 2 timeframes stated in paragraph 2.1.1 above. 2.2 Option 1: Design, Abatement of Hazardous Materials, and Renovations of the Dining Area & associated offices. Total occupancy anticipated for the dining area is 165 (120 in the large dining room, 45 small dining room). Period of Performance to be completed within 365 calendar days from the award date of this option. Within the 365 calendar days, actual field construction is only allowed to occur for 120 calendar days from start to finish. This includes demolition. 2.3 Option 2: Abatement of Roadway Ceiling: Remove the entire roadway ceiling from east power plant (EPP) to west power plant (WPP); Clean all structural steel and bottom of second floor; Clean above ceiling on south side of roadway to rock; Make a 2 hour rated corridor. That is ensure walls and 2nd floor deck to ground are 2 hour rated; Paint structural steel and second floor. Period of Performance shall be 540 calendar days from the award date of this option. 2.4 Option 3: Abatement of Asbestos in Power Plant: Clean entire EPP from top down including rock ceiling and rock wall surfaces and the floor area; Clean all structural steel, buildings, and equipment exteriors; Clean EPP mezzanine switch gear area – rock ceiling and rock wall surfaces only, equipment and floor do not require cleaning; Clean exhaust tunnel ceiling and walls, encapsulate or clean floor. Period of Performance is 365 calendar days from the award date of this option.
All Saints Parish Sign 9300 Stonewall Rd, Manassas, VA 20110
The Arlington Diocese (- Amnd. 0) CMD: Ddg:
Concrete Church sign with lights and a brick veneer
Two-Phase IDIQ for Nationwide MEDCOM, Sample Proj:DB Repair Preventive Medicine Bld 8420, Ft.Knox KY PHASE II D/B IDIQ for Healthcare Facility Design/Repair/Construction for MEDCOM Nationwide
US Army COE, Mobile AL (W91278-15-R-0020 Amnd. 9) CMD: Ddg:
SEED PROJ: The objective of this project is for the Contractor to provide all labor, materials, equipment and utilities necessary to complete a Design, and the Repair/Renewal effort as specified, for the Preventive Medicine Bldg. This requirement shall be a total turnkey deliverable. No transition space is required, the building is unoccupied, and contains no hazardous materials. The existing Preventive Medicine Building is approximately 5,900 sf and located at: 2001 Base St, Ft. Knox, KY. The building was originally constructed as a soldier barracks. The building is over 42 years old, with aging infrastructure and failed/failing systems, finishes, etc. A complete repair/renewal is required to meet the mission for Preventive Medicine, as well to correct all deficiencies and failed/failing conditions. IDIQ Nationwide MEDCOM: The primary purpose of this contract is to provide a full range of construction services to include design/build renovation, repair and new construction for MEDCOM medical treatment facilities (MTF) and medical research laboratory facilities to provide quick, cost effective responses to requirements for MEDCOM facilities, primarily at military installations. Potential projects include, but are not limited to, work inside both permanent and temporary facilities some of which include the following types: medical centers, community hospitals, medical clinics, dental treatment facilities, veterinary treatment facilities, medical office buildings, medical research laboratory facilities, medical warehouses, and various other facility types in direct support of the MEDCOM mission. As the facilities will typically be in full operation, the contractor will be required to minimize interference with the daily operation of the facilities and will be required to implement infection control processes and to comply with Joint Commission requirements for construction work in occupied medical facilities. The term of the contract is limited to a one year base period and two (2) twelve month options.
D/B Modernization of USDA Foreign Disease Weed-Science Research Facility S-17-0005 USDA-ARS-FDWSRL, 1301 Ditto Avenue, Frederick, Maryland 21702 >$60 Million
Department of Agriculture ARS (AG-3K25-S-17-0005 Amnd. 0) CMD: Ddg:
Besides the fact that the research at Fort Detrick is spread over many small and inefficient buildings, the current research facilities are approximately 30 years old and have exceeded their service life. The project scope includes constructing a new BSL-3 Plant Pathogen Containment facility consisting of a Laboratory, Head house, and Greenhouse and will be adjacent to existing Buildings 1301-1309 complex. The new facility will be approximately 50,000 GSF and will serve as a replacement for Buildings 374 (BSL-3 Plant Pathogen Containment) and 390 (Effluent Decontamination System), which has a combined total of 18,467 GSF. The proposed construction at Fort Detrick will be performed on an active research campus located on a secure military installation. The Estimated Cost of Construction for the Modernization of the FDWSRL at Fort Detrick, Frederick, MD, is more than $60 million. Prospective Design Build Contractors are required to provide an Operations and Maintenance Plan. The Bridging Documents (BD) will consist of a complete 65% design submission. The Design Build Contractor (DBC) will use the BDs as the basis to complete a set of construction documents. As stated above, the purpose of this Sources Sought notice is to identify prospective Small, SDB, SDVOSB, HubZone, WOSB and Certified 8(a) firms to provide Design Build services associated with the Modernization of the FDWSRL. The current goal for ARS is to complete the BDs before the end of April 2017, and to award the construction contract in the January 2018 timeframe. NO SOLICITATION EXISTS. THIS REQUEST IS INTENDED ONLY TO IDENTIFY SOURCES OF PROSPECTIVE DESIGN BUILD FIRMS. The Government does not intend to award a contract on the basis of this sources sought announcement. The deadline to respond to this notice is December 30, 2016, 3:00 pm Eastern.
GSA IDIQ Construction Svcs-Design & Construction Svc 16-GX-1012 -Sources Sought Washington DC Area $200,000 - $8 Million
General Services Administration (GS11P16GX1012 Amnd. 0) CMD: Ddg:
GSA anticipates awarding up to 15 contracts.Each contract awarded will contain a guaranteed minimum amount for the base period to be identified in the solicitation. A single task order award could potentially range from $2,000 to $8,000,000. Primarily, task orders will consist of repair/alteration and tenant finish projects for the GSA and other government agencies in occupied federally owned or leased buildings. A typical task order could contain some or all of the following: modifications to architectural components and related electrical systems associated with, but not limited to ceilings, walls, floors (including access floor systems), roofing systems, millwork and wall covering. Work may also include modifications and replacement of mechanical systems to include, but not be limited to: air handling units, chillers, boilers, ductwork systems and accessories, piping systems (including pumps), HVAC system controls, fire protection sprinkler systems and accessories, and plumbing equipment/accessories. In addition, scope may also include work on electrical systems including, but not be limited to lighting systems, primary and secondary power distribution systems and transformers. Special competencies will be required for any work involving membrane roofing, asbestos abatement, PCB removal and/or elevator work. Interested parties shall be capable of providing the services associated with the aforementioned competencies.
FBI Mid-Level MACC IDIQ Various locations $150k - $30 million
FBI (DJF-17-1200-R-0000045 Amnd. 0) CMD: Ddg:
The Federal Bureau of Investigation (FBI) has determined the need to procure a suite of Indefinite Delivery Indefinite Quantity (IDIQ) Regional Multiple Award Construction Contracts (RMACCs) to perform construction on a regional basis and nationwide. The contracts will meet a majority of the FBI infrastructure needs for construction, remodel, and renovation for projects with a construction value between $150,000.00 and $30,000,000.00 within the 50 United States and its territories. These contracts are intended to provide prompt responses on an as-needed basis for routine and emergent requirements. The contracts offer a streamlined approach to construction contracting and ongoing competition between qualified contractors. The scope of work will include, but is not limited to, real property repairs, maintenance, and general construction, and demolition. Facilities include, but are not limited to, operations buildings, hangars, commercial buildings and their mechanical and electrical systems, site utilities, and roadways. Design/Build, Design/Bid/Build, and Early Contractor Involvement (ECI) project delivery methods will be used. It is anticipated that this RMACC will have four (4) pools of three to five (3-5) contractors. Pool #1 will be a nationwide pool consisting of other than small businesses who will bid on projects with an estimated value of greater than $4,000,000.00. All other pools will be established for a specific location and set-aside for small businesses with estimated project construction values of $150,000.00 to $4,000,000.00. Pool #2 will support the Redstone Arsenal (RSA) region centered in Huntsville, AL. Pool #3 will support the National Capital Region (NCR). Pool #4 will support the Criminal Justice Information Services (CJIS) region centered in Clarksburg, WV. Projects at all other nationwide and territorial locations under $4,000,000.00 construction costs will be made available to all small business pools. Projects under $150,000.00 may use this vehicle if the Procuring Contracting Officer (PCO) determines that it is in the Governments best interest to use this vehicle. Each of the contracts will include a base period and four option periods. The minimum guarantee for each individual contract will be $5,000. The anticipated aggregate capacity for the RMACC is $800,000,000.00. The government has determined that the Two-Phase Design-Build Selection Procedure outlined in FAR Subpart 36.3 is appropriate for this procurement.
FRR MATOC Design/Build Repair Bldg. 416, JB Myers-Henderson JB Myers-Henderson, VA
Dept of the Army, Huntsville, AL (24 Amnd. 0) CMD: Ddg:
This design-build project will repair unaccompanied enlisted barracks Building 416. This building is in failing condition due to aging. This is a VOLAR style barracks building constructed in 1977. This project covers building 416 complex which consists four (4) wings (416-A, 416-B, 416-C & 416-D) and a common use building. This project repairs the failed and failing components of the barracks building 416. Total SF is approximately 63,377 not including a basement section under each wing and the common area facility (2,768). Systems to be repaired include exterior walls, doors, pooches, and soffits, exiting roof. Roof and wall insulation will be repaired to current standards, new blast windows will be installed, and AT/FP measures will be retrofitted. The buildings utility systems, electrical systems, plumbing systems and HVAC systems to be repaired by replacement. Ceiling mounted light fixtures will be provided. Additional repairs include existing interior doors and walls, some reconfiguration to maximize capacity and improve efficiency of interior space. Leaking plumbing lines, HVAC ductwork, chilled and heating water systems will be repaired in accordance to table 2-1 of DA PAM 420-11. Walls and ceiling surfaces to remain will be repaired, finished and painted, flooring throughout will be repaired or replaced as required. Structural elements damaged by mold and water leaks will be abated or replaced to meet health standards and handicap access will be provided to common areas. Removal of Asbestos containing material (ACM) and lead base paint (LBP) will be abated/required in this repair project. Due to the water intrusion, some of the walls, ceilings and flooring have been damaged. Mold problems persist throughout Building 416. No major repairs have been made to this building in over 20 years. The barracks building does not meet current requirements for protection against progressive collapse. Blast windows will be required to be installed due to the proximity of the building with the installation perimeter. Open balconies will be eliminated.
GSA 11 Renovation of 9th Floor RMB USSS Headquarters USSS Headquarters, 950 H Street NW, Washington, D.C. $150,000-350,000
GSA (47PM0419Q0007 Amnd. 0) CMD: Ddg:
USSS 9TH Floor PID RMB SCIF Renovation. Design/Bid/Build - Per the scope of work, provide all labor, materials, equipment and supervision to renovate specific areas of the USSS 9th Floor PID RMB SCIF. Period of Performance is 120 days - PoP: 11/28/2018 - 03/28/2019
GSA 11 D/B OIT Consolidation Project Phase 1 Demo of Suites 1515, 1525 and 153, Prettyman Courthouse 333 Constitution Avenue, NW, Washington, DC 20001 $250,000 to $400,000
GSA (47PM0519Q0008 Amnd. 3) CMD: Ddg:
PROJECT GOALS 4.1 Goals: The goals of the project include, but are not limited to: A. To prepare the required documentation and procure the work required to demolish Suites 1513, 1525, 1530 and all associated offices, as identified on attached Drawings 1 and 2, to enable a new U.S. District Court Office of Information Technology (OIT) suite to be built. B. To establish work order priorities in order to carry work in a phased approach, taking into account the needs and requirements of the tenant agencies and the realities of budget constraints and limitations. C. All work disruptive to tenants shall be performed during "off-hours" (i.e. evening and night) and on weekends. The Contractor shall coordinate all work activity with the Building Manager and the Contracting Officer's Representative to ensure that proper security and access arrangements are made with minimal impact on the construction schedule. D. Full compliance with all building's security regulations. E. Provision of the necessary cutting, patching, and repair of the existing buildings. F. Demolition shall be in accordance with OSHA and applicable building code requirements. C. To preserve and enhance the cultural property.
AFICA East D/B Repair Hangar Building 290, Tyndall AFB, FL 1275 Florida Avenue, Tyndall AFB, FL 32403 >$10 Million
Dept of the Air Force (XLWU 19-8103 Amnd. 0) CMD: Ddg:
The purpose of the Tyndall Air Force Base (TAFB) project XLWU 19-8103, Repair Hangar Building 290, is to rapidly repair hurricane damage and to bring the building and its supporting facilities into full compliance with current building codes, including but not limited to the DoD Building Code, UFC 4-211-01 Aircraft Maintenance Hangars, and the portion of the Florida Building Code that contains the High Velocity Hurricane Zone (HVHZ) provisions. (TAFB will be treated as a Wind Zone 4 located site) Work on supporting facilities include external building fixtures, building utilities within the Points of Demarcation (POD) for privatized utilities, and work within the remotely located Base Energy Management Control Center (EMCS). Time is of the essence. This project includes the acquisition and installation of structures to temporarily house personnel and equipment, which will allow the facility missions to continue while the permanent facility is under construction. Some spaces are certified for the handling and storage of classified information and/or materials. Following construction, all purchased swing space facilities are to be taken out of service, secured for long-term storage, and removed to a location on TAFB once they are no longer needed for the project. All rented swing space facilities are to be taken out of service, secured for transport, and removed from TAFB. Building 290 is located at 1275 Florida Avenue, Tyndall AFB, Florida 32403. It is an approximately 59,000 sf aircraft hangar primarily for the general maintenance of 5th generation fighter aircraft (F-22 and/or F-35), which incorporates normal and Special Access Program Facility (SAPF) administrative spaces. Building 290 is located on an active DoD airfield.

Subs & Vendors

All projects are available in our plan room for review.
Fax your bid to 301-881-4938 or call 301-881-5120 for further information.

Let us know below which jobs you will quote: