Clandestine Laboratory, Training and Research Center, Department of Justice DEA, in Quantico, Virginia
A General Contractor Serving Washington, DC Metropolitan Area Since 1951

BID SCHEDULE AS OF MONDAY 11/23/2020

Bid Date Project Location Estimate
11/25/2020 GSA 11 D/B DOS Storage and Office Build Out, Franconia Warehouse Bldg. 7A Bay 7B 6810 Loisdale Road, Springfield, VA 22150 $750,000-900,000
1:00P GSA (47PM0221Q0007 Amnd. 1) CMD: Ddg:
Phase 1 is expected to start immediately following award and spec submittals. Phase 2 will be in design while Phase 1 fencing is being installed. Phase 1 – Fencing and Racking Chain Link Fence 16' High Including Gates, Hardware (Dimensions are 191’ x 157’) • Install approximately 696 ln feet of 16’ exterior fencing with privacy slats • Install 314 ln ft interior fencing • Install 5-10ft rolling gates around the exterior fence Warehouse Racking • Purchase and install approx. 850 ln ft of racking. Installation to include bolting racks into the warehouse floor. Racks should have 3 levels of shelving. Top shelf no higher than 14’ high. Equipment (forklift) Charging Station will be set but will need to be relocated during design (Spec attached) • Install two (2) dedicated circuits. Power for one (1) electric forklift and one (1) electric walk-behind pallet jack. Phase 2 – Modular Office Build Out and related activities Relocate Equipment Charging Station based of Design Remove the section of fencing needed to be replaced with modular unit partition pending design review. 3 work station Modular Air Conditioned Office w/Metered Elec. Electrical Power Feed Tele/Data Drop Cable Raceway @ Card Reader Lighting Adjustment (verify on site) Sprinkler System Upgrades - The design-build contractor shall secure the services of a fire protection engineer to evaluate the existing sprinkler system to determine its adequacy for protecting the proposed storage commodities in accordance with the requirements of NFPA 13. The fire protection engineer shall evaluate the commodities to be stored and the manner in which they will be stored (racks, encapsulated, storage height, etc.). Design and installation for modifications to the building fire alarm system to provide FA notification in accordance with NFPA 72. NOTE: The only hazardous material stored in this facility will be a small munitions box that will be stored in a cabinet provided by the DOS.
11/25/2020 US Treasury IDIQ MATOC Const Services Small Business, SEED: Main Treasury North Court Roofing Multiple Treasury Buildings, 1500 Pennsylvania Ave., NW, Washington, DC 20220 $250,000-$500,000
2:00P US Treasury (2032H320R00005 Amnd. 10) CMD: Ddg:
This contract will be awarded to multiple small business contractors to perform multiple award task order construction services to support the Department of Treasury Departmental Office Treasury Operations (TO). Construction task will be performed on multiple Treasury Buildings located in Washington, DC. The scope of work for the projects executed by Task Orders under the contract will include various construction improvements requiring the contractor to furnish all the necessary supervision, labor, parts, tools, materials, equipment, etc., (except as may otherwise be provided for in the specifications) to perform design-bid-build construction projects such as facility repair/alteration, and real property repair/alteration projects on an as needed basis in an expeditious manner. Construction Project types may include, but are not limited to, the following: •Office, facility upgrades, interior space, renovations and reconfigurations including demolition; construction of walls and ceilings; installation or modification of HVAC, lighting, electrical, telecom, furniture removal, fire alarm, sprinkler and other systems, flooring, and renovation to meet ADA and Life Safety codes. Work may include renovation of occupied and unoccupied office areas and may include changes to finishes or may include major demolition and rebuilding. •Repairs, renovations, and upgrades to the building's exterior including the roof, exterior marble facade, columns, exterior lighting, plazas, fountains, planters, and signage. The construction work includes tasks in various trades such as carpentry, asbestos abatement/removal, demolition, mechanical, electrical, plumbing, roofing, concrete masonry, welding, telecommunication, furniture removal, and paving.
11/25/2020 GSA 11 D/B Kitchen & Seating Area Upgrades at HH Humphrey Bldg 200 Independence Ave., SW, Wash., DC 20407 $5-10 Million
2:00P GSA (47PM0421R0002 Amnd. 3) CMD: Ddg:
The project shall be based on the provided concept drawing, program of requirements, customer requirements documents, and the Criteria Governing Design. The SOW project area at current state is out-to-date with kitchen equipment that does not meet today’s standards for efficiency. Additionally, the current layout does not meet mission requirements for food prep, storage, and service to serve in the most efficient way to tenants and visitors. This project will correct those aforementioned shortfalls to meet Tenant Agency current and future mission needs for this space. The project objectives are to fully renovate the kitchen and seating area so as the Tennant Agency can 1. Provide and updated aesthetic modern look to the kitchen and seating area, 2. Provide cutting edge kitchen equipment to improve Tenant Agency mission objectives for the kitchen area, and 3. Provide enhanced customer service to tenants and all visitors.
12/7/2020 Perimeter East Building Renov and Upgrades Const Project at SSA Complex Social Security Administration,Woodlawn Campus, 6201 Security Blvd., Baltimore, MD 21235 $30-50 Million
1:00P GSA, Phila PA (47PD0121R0001 Amnd. 6) CMD: Ddg:
The Perimeter East Building (PEB) was originally constructed to serve as the main data center for the Social Security Administration. The data center function has since moved out of the building and the program for the building seeks to convert the floors to modernized office space, using a space utilization rate of 150 usable square feet (USF) per seat. The project scope consists of approximately 90,000 SF of renovations, tenant improvements on the 4th floor, two new exterior stair tower structures, smoke control system upgrades for the PEB lobby, and new HVAC equipment on other floors as indicated in contract documents, building automation controls, upgrading existing BAS controls at the PEB and PEUB Building. As part of the demolition, identified hazardous material removal is expected, including asbestos containing materials and lead based paint. In addition, the project will include a renovation to the PEB cafeteria kitchen and serving area. There is also an alternate for a full mechanical infrastructure upgrade, which would include installing four new rooftop AHUs. Other goals for the project include but are not limited to the following items: • Creating an open and welcoming office environment; • Increasing daylight and exterior views for the occupants of the open office areas and breakrooms; • Creating more conference rooms and teaming areas; • Creating work areas with good acoustics.
12/15/2020 GSA 11 D/B FBI Concrete Repairs at Hoover Bldg. Parking Garage 935 Pennsylvania Ave., NW, Washington, D.C. 20535-0001 $1-5 Million
1:00P GSA (47PM0121R0003 Amnd. 1) CMD: Ddg:
The subgrade concrete parking garage at the JEH is experiencing advanced delamination, spalling, and exposed rebar in several areas of the parking decks and ramps. Areas are deteriorated to a point where vehicles cannot park due to structural integrity concerns. GSA has conducted minor repairs and alterations to undertake necessary interim repairs at locations where the concrete slabs exhibited the most advanced deterioration. Removal or relocation of electrical and low voltage communication lines, water, air and fuel lines, and heating, ventilation, and air conditioning equipment may be needed. Removal of spalling concrete, deteriorated/unusable rebar replacement is necessary as needed. The parking garage will remain in service throughout the project. * The project is design-build type delivery * The objective of the project is to perform emergency structural repairs of the sub grade concrete parking slabs, columns, beams and walls. * The project period of performance is 390 calendar days. This is comprised of 150 calendar days of Design Stage work, 210 calendar days of Construction Stage Work, and 30 calendar days of Project Closeout activities. * The project has a current estimated Contract Award of September 2020. * Construction Start is estimated to begin May 2021. * All construction project work will occur outside of normal business work hours 6:00am-6:00pm. The inspector’s position will be required to work part time and/or full time (hours will vary) during non-business hours (6:00pm - 6:00am) onsite during allconstruction activities. The Project Manager can work during normal business hours. The project is not a change in use of space. The project is not a change in occupancy.
Washington Aqueduct Second High Reservoir Maintenance and Improvements- PreSolicitationNotice 4/9/20 Washington Aqueduct, Intersection of Van Ness Street and 44th Street, NW, Wash., DC 20016 $5-10 Million
Dept of the Army (W912DR20B0006 Amnd. 0) CMD: Ddg:
The project consists of implementing upgrades and improvements to the Second High Reservoir to address operational and sanitary survey issues previously identified. This will result in improved water quality and operation within the distribution system. The work includes the replacement of a brick Sample Building; the replacement of the 24” drain line; installation of mechanical mixers; sealing of all interior joints and cracks; installation of a spread spectrum radio communications antenna; installation of a roof sub-drainage system and the replacement of the perimeter fence. This reservoir is a critical component of the distribution system and so the reservoir outage period is restricted. An experienced contractor with resources and expertise to handle the following project constraints is needed: 1. The reservoir roof surface has limited weight restrictions and can only be taken out of service for three (3) months. All work needing to be performed inside the reservoir has to be completed within that time frame. 2. The demolition and re-building of brick Sample Building must be done within the limited outage window while the reservoir is out of service. 3. Access into the reservoir structure is limited and all work therein is considered confined space work. 4. The reservoir is located in a residential neighborhood and so noise ordinance requirements must be strictly adhered to. 5. The existing security server and associated equipment is to be removed and re-installed by a professional security contractor
FRR MATOC USACE South Atlantic Division HQ Hallway Restoration and Painting, Atlanta - DRAFT SOW USACE South Atlantic Division Headquarters, 60 Forsyth St. SW, Atlanta $100K-250K
Huntsville Army COE (1 Amnd. 0) CMD: Ddg:
The Contractor shall provide all personnel, equipment, tools, vehicles, materials, supervision, subcontracts, and other items and services, except as specified as Government- Furnished, necessary to perform hallway restoration, wallpaper stripping, sanding/patching and repairs to the wall as necessary, priming and painting is required as defined in this Performance Work Statement (PWS). The award for services under this PWS shall be limited to the services identified in the contract line items awarded in the contract and its modifications. 1.1. BACKGROUND. The United States Army Corps of Engineers South Atlantic Division (SAD) Headquarters which occupies two (2) floors of the Sam Nunn Atlanta Federal Center physically located at 60 Forsyth St. SW, Atlanta, GA. The Sam Nunn Atlanta Federal Center was completed in 1997 and common wall areas on the ninth and tenth floors have not been updated since that time period. The contractor should expect variations in the exact boundaries of the walls where services are to be performed but is estimated to encompass 13,000 square feet. The contractor must maintain flexibility because the building floors where services are requested may or may not occupied due to public health concerns. The period of performance shall be a period 45 days from date of award.
FRR MATOC Rivanna Station Break Room Renov, Controls Upgrade,Roof Repairs, Charlottesville-DRAFT Rivanna Station - Charlottesville, VA
Huntsville Army COE (1 Amnd. 0) CMD: Ddg:
The objective for this Statement of Work (SOW) is to provide all management, labor, equipment and material necessary for renovation and upgrades for the existing break room(s), roof repairs, and switch gear controls upgrade located at Rivanna Station - Charlottesville, VA. The Contractor's design and construction shall comply with the specifications and requirements contained herein. The design and technical criteria cited within this SOW establishes minimum standards for design and construction quality.

Subs & Vendors

All projects are available in our plan room for review.
Fax your bid to 301-881-4938 or call 301-881-5120 for further information.

Let us know below which jobs you will quote: